What the Purchase Order Should Lock.

The inspector was not in the design meeting. They have the purchase order, the sealed sample and a tape. Write the order for that person.

MANLOR Development Team · 20 October 2026 · 8 min read

Write it for the person with the tape

Design will remember what was meant. The inspector will not. If the purchase order, the sealed sample and the tech pack disagree, say which one wins. On our floor the sealed sample wins, and the order should say so. Otherwise the argument happens in the packing area, which is a bad place to interpret a sketch.

Style, colour, size — not assorted

Pieces by style, by colour, by size. If the size split is not known, the order is not ready to cut. Assorted becomes whatever marker was already on the table. We do not publish one size split for every garment; yours has to be on the order, in writing, before spreading. The packing list has to keep that split. A list that regroups sizes the order separated will fail the warehouse appointment, even when the sewing was right.

Colour is a dye lot, not a name. If two lots are close but not the same, they do not share a carton unless a shade band is agreed and marked. The practical controls are in avoiding colour variation.

Name the sealed sample

Style code, the date it was sealed, and who holds the duplicate. Bulk is matched to that garment. Not to the proto, and not to the flat sketch if they have drifted apart. What had to be frozen before that signature is in what to freeze before the seal.

AQL, who inspects, and when

Name the AQL, the defect classes, and who may stand at the table. Our published standard is AQL 2.5 for major defects and 2.0 for minor defects. The minor figure is tighter than the 4.0 still printed on a lot of general apparel orders. If your manual says otherwise, the purchase order has to say so. A blank will be read as our published standard, not as the last factory's habit.

Write critical defects as zero: a needle, a broken snap, a missing legal label. Your own QC, or a third party you name, is welcome inline or at the end. Final inspection starts when production is complete and at least 80% of the order is packed. Put that sentence in the order, so nobody calls an inspection on a half-empty line and then disputes the result. How the tables work is in AQL for premium apparel.

Payment, and the day a claim is still a claim

Our published term is 30% with the order and 70% at shipment by T/T, with a letter of credit for key accounts. Repeat the trigger on the purchase order. As discussed is not a trigger. Trade term too: FOB, EXW or DDP, and where.

Claims: we publish 20 days after the goods arrive at your warehouse, with photographs and quantities. A verified quality issue is refunded according to the case. If you need a different window, write it. The email thread will not be what accounts reads in month three.

Also write who pays a re-inspection if a lot fails. Silence becomes a negotiation on the day of the failure, which is the worst day to invent a rule. We do not publish a site-wide defect rate, and a purchase order should not invent one either. Each order gets its own report: measurements, defects, photographs.

A clause list worth pasting

Not a contract template. The lines that, left blank, are where premium orders actually break. Our figures live on factory facts. Yours, if they differ, have to be the ones on the order.

If the line is blank, this is what happens
PO lineWriteIf you leave it blank
StandardSealed PP: style, date, who holds itBulk is argued against a proto or a sketch
QuantityStyle, colour, size, piecesThe marker decides the sizes
AQLMajor, minor, critical, and whose tableThe factory standard is assumed
InspectionWho may inspect, and at 80% packedA half-finished line gets called a final
ShadeOne band per carton unless markedLots get mixed and the rail shows it
MoneyDeposit, balance, and the event for eachShipment waits on a verbal promise
ClaimDays after arrival, and what you must sendThe window is whatever someone remembers

Frequently asked questions

What should a purchasing manager lock on a clothing purchase order?

The sealed sample, quantity by style, colour and size, the AQL and who inspects, when the goods are ready to inspect, the payment triggers, and the claims window. Assorted sizes and similar to the proto are not standards.

Whose AQL applies if the PO is silent?

The factory's published standard. Ours is AQL 2.5 for major defects and 2.0 for minor defects. If your quality manual differs, the purchase order has to say so.

When can final inspection be called?

When production is complete and at least 80% of the order is packed. Calling it earlier produces an argument, not a result.

Start a Related Project

From the Journal

Start a related project.

Put this guide into practice — share your brief and our development team will reply with next steps.

What are you looking to develop?

Start a Related Project