Clothing Production Timeline & Development Calendar

Every collection runs the same sequence — brief, fabric, sample, fit, sealed sample, bulk, inspection, shipping. Work back from the day goods must reach your warehouse to find the day development has to start.

Planner

Work back from your warehouse date.

Choose when goods must arrive, how the fabric is sourced, how many fit rounds to allow and how they ship.

Start development by1 Feb 202726 weeks from brief to warehouse

Planned stages and the latest date each can start
StageWeeksStart byFinish byStarts when
Brief review & quotation11 Feb 20278 Feb 2027A complete brief is received
Fabric & trims68 Feb 202722 Mar 2027Fabric direction is agreed
First sample222 Mar 20275 Apr 2027Brief, fabric direction and sample fee are confirmed
Fit rounds45 Apr 20273 May 2027Your written fit comments are received
Pre-production sample23 May 202717 May 2027Fit is approved and bulk fabric and trims are in house
Bulk production517 May 202721 Jun 2027The last of: PPS approval, bulk fabric passed, deposit received
Final inspection & packing121 Jun 202728 Jun 2027Production complete, at least 80% packed
Shipping to your warehouse528 Jun 20272 Aug 2027Inspection passed, balance settled as agreed

Planning allowances, not a quotation. Sampling is typically 9–12 days and bulk 25–35 days from its start point. Your written schedule replaces every figure here — what starts each stage.

Season windows

The seasons we are planning.

Indicative windows for in-store dates of January–March (SS) and July–September (AW), confirmed per project.

AW27

Autumn / Winter 2027

Open for concept & fabric development
Concept & fabric
Oct – Dec 2026
Proto & fit
Jan – Feb 2027
Pre-production & bulk
Mar – May 2027
Delivery
Jun – Jul 2027
Plan AW27 development
SS27

Spring / Summer 2027

Final development & bulk — limited new styles
Concept & fabric
Jun – Jul 2026
Proto & fit
Jul – Aug 2026
Pre-production & bulk
Sep – Nov 2026
Delivery
Dec 2026 – Jan 2027
Plan SS27 development

What moves the date.

A season is late because of its slowest step.

DriverWhat happensHow to protect the date
Custom fabricWeaving, knitting or dyeing to order adds weeks before the right cloth exists.Agree the fabric route first; cut the proto in the closest available cloth while bulk fabric is developed.
Fit roundsEach round needs written comments, a pattern correction and a new sample.Send one consolidated set of comments per round, with measurements and photographs.
Late commentsThe next sample starts when written comments arrive, not when the sample does.Agree a reply window for each round in the schedule.
Trims and labelsWoven labels, branded hardware and custom buttons have their own lead times.Approve label artwork and trim cards with the fabric, not after fit.
Laboratory testsMany programmes need wash, colourfastness or composition results before bulk.Test bulk fabric as soon as it arrives — materials testing.
Chinese New YearMills and factories close; output typically stops for two to four weeks.Seal the pre-production sample before the holiday, or start bulk after it. The planner adds this buffer.
National Day, 1–7 OctoberA week-long public holiday that pauses mills and logistics.Keep fabric deliveries and approvals out of that week.
Shipping modeSea freight to the US or Europe takes weeks; air takes days at a higher cost per piece.Decide the mode before the ex-factory date is fixed.
Questions

Timeline FAQ.

How long does clothing production take from design to delivery?

For a new premium style, plan roughly four to six months from a complete brief to goods in your warehouse. Sampling typically takes 9–12 days per sample and bulk typically 25–35 days from its start point; the rest of the calendar is fabric, fit approvals, inspection and shipping.

When should we start an autumn/winter collection?

Start from the coats and any custom cloth: these usually begin nine to twelve months before an autumn delivery, while shirts and styles in available fabric can start later.

Can the timeline be shortened?

Yes, by removing work rather than squeezing it: available fabric instead of custom development, private label on resolved blocks, fewer fit rounds, or air freight. A date that skips the sealed pre-production sample is not a plan.

Are the planner dates a commitment?

No. They are planning allowances. Each date for your order is fixed in the written development schedule once the fabric route and style count are known.